Lagoon lowering is scheduled to commence April 4, 2022. Lagoons 3, 4, and 5 will need to remain down longer than usual to accommodate much-needed repairs to the concrete columns of the Bayview Weir located in Lagoon 5. These repairs are expected to require a 60-working day window. If repairs are completed earlier than planned, Lagoons 3,4 and 5 will be refilled early than noted below.
We will begin filling the Lagoons as follows:
- Lagoons 1 and 2 – May 16, 2022
- Lagoons 3, 4 and 5 – July 13, 2022