2022 Lagoon Lowering Dates/Bayview Weir Repairs

Lagoon lowering is scheduled to commence April 4, 2022.    Lagoons 3, 4, and 5 will need to remain down longer than usual to accommodate much-needed repairs to the concrete columns of the Bayview Weir located in Lagoon 5.    These repairs are expected to require a 60-working day window.   If repairs are completed earlier than planned, Lagoons 3,4 and 5 will be refilled early than noted below.

We will begin filling the Lagoons as follows:

  • Lagoons 1 and 2 – May 16, 2022
  • Lagoons 3, 4 and 5 – July 13, 2022